The All-Star Team at Memorial City Plazas is working hard to ensure tenants are as comfortable as possible during the renovation. Frequently Asked Questions are provided below for your convenience, but please email
mcprenovations@mcityoffice.com with any additional questions, or feedback during the renovation process. In addition, the Memorial City Plazas team will provide progress updates on select Thursdays along with a with special treats! We appreciate your patience as we renovate & rebuild for the future.
11/28/22 Update:
Exterior
- Site Demolition 97% complete
- Site grading and compacting ongoing
- Installation of pavement has begun outside 840 Gessner
800 Gessner
- Curtainwall glass panels installation ongoing
- Subflooring installed and finishing work has begun in the Gym.
- 2nd floor conference rooms walls are painted, glass walls are framed, and carpet is installed
- New mailroom is 98% complete
- Sheetrock ceilings installed in 2nd floor lobby and corridors
- New restroom doors and mechanical room doors installed on 2nd floor
- Tile flooring installed on the 1st floor (currently covered with protective covering)
- Elevator call buttons on 1st & 2nd floors moved to temporary platform to accommodate elevator lobby finish work
820 Gessner
- Curtainwall glass panels installation ongoing
- New mailroom is open. Permanent door will be installed in the coming weeks
- Construction of renovated 1st floor restrooms ongoing
- Training Center interior walls are framed and sheet-rocked
- Sheetrock ceilings installed in 2nd floor lobby and corridors
- New restroom doors and mechanical room doors installed on 2nd floor
- Tile flooring installed on the 1st floor (currently covered with protective covering)
- Elevator call buttons on 1st & 2nd floors moved to temporary platform to accommodate elevator lobby finish work
- Elevator cab renovation has begun in one high-rise elevator cab
840 Gessner
- Upcoming: delivery of furniture, rugs, accessories, and artwork; back-painted glass panels for elevator lobbies; front vestibule finishes
We appreciate your patience as we renovate and rebuild for the future! If you have questions about the renovations, please email: mcprenovations@mcityoffice.com, and as always, if you have any concerns, please call the management office at 713.821.5400.
FAQ
- How long will the renovations take?
A: Construction will start on February 26th and will approximately end in late Fall of 2022.
- How will access to offices & the parking garage be impacted during the renovation process?
A: Existing access to the parking garage and skybridges is expected to remain throughout the construction period as the majority of the improvements will be focused on the 1st floor lobbies and surrounding exterior areas. The Ingress/Egress plan for the lobby areas will be announced prior to the construction commencement and as the project progresses, modifications and adjustments will be promptly communicated to building tenants.
- Will security be increased during certain phases of the project?
A: Security remains a high priority for MetroNational and we will be evaluating and adjusting security presence and coverage areas as the renovation project progresses.
- What amenities are being added to the building, and will renovations impact any current amenities?
A: The lobby renovation focuses on enhanced amenities and tenant wellness. Examples of the new amenities include a fitness center, full-service conference center and meeting rooms, updated lobbies with expanded seating areas and touchless technology. In addition, while the existing Skyline deli will remain open during construction, the renovation includes the addition of a Common Bond Café concept at 820 Gessner.
- How and where will deliveries be made during the renovations?
A: The back drive between the buildings and garage that provides access to loading docks for large deliveries will remain open. Tenants will be notified in advance of closures to front entrances, at which time, all deliveries and visitors will be directed to an alternative entrance.
- What is the quickest way to keep up-to-date?
A: Download the MCity app on your mobile device for the latest renovation updates. Download the MCity app.
Click here to view the presentation slides from the Reimagine Memorial City Plazas Luncheon.